707.4, Location, is hereby deleted in its entirety and the following provisions shall be substituted therefor:

Each horizontal drainage pipe shall be provided with a cleanout at its upper terminal, and each run of piping, that is more than one hundred (100) feet (30,480 mm) in total developed length, shall be provided with a cleanout for each one hundred (100) feet (30,480 mm), or fraction thereof, in length of such piping.

Exceptions:

(1) Cleanouts may be omitted on a horizontal drain line less than five (5) feet (1,524 mm) in length unless such line is serving sinks or urinals.

(2) Cleanouts may be omitted on any horizontal drainage pipe installed on a slope of seventy-two (72) degrees (1.26 rad) or less from the vertical angle (angle of one-fifth (1/5) bend).

(3) Excepting the building drain and its horizontal branches, a cleanout shall not be required on any pipe or piping that is above the floor level of the lowest floor of the building.

(4) An approved type of two-way cleanout fitting, installed inside the building wall near the connection between the building drain and the building sewer or installed outside of a building at the lower end of a building drain and extended to grade, may be substituted for an upper terminal cleanout.

(5) A cleanout shall be installed above the flood level rim of all urinals with integral traps.

(Ord. 20257 § 35, 8-18-20; Ord. 19829 § 31, 7-9-13. Formerly 14.35.300.)